摘要 地下采矿必然会引起采空区围岩的崩塌,围岩向采空区的移动可能涉及到地表,造成地表的陷落.采用充填法,留矿柱法等措施能够减轻地表的沉降.本文借助Ansys进行网格划分后,将其导入Flac数值计算软件中.Flac软件能模拟开采、回填、再向下开挖、再回填等过程,与实际开采和充填一致.对金山店铁矿东区分别进行不充填、20%充填、50%充填的地下开采进行模拟,研究采矿引起的地表沉降问题.分析得出下盘稳定性好于上盘,水平位移和垂直位移在量级上相当,充填越多越能减轻地表沉降. Underground mining will cause the collapse of goaf surrounding rocks and movement of surrounding rock to goal may effect on the surface, so as to cause surface collapse. The measures such as pillar method and filling method can reduce the settlement of the ground surface. With Powerful modeling and meshing capabilities of Ansys software, the grid is meshed by Ansys and then imported into Flac software. Flac can simulate the mining and filling; and then mining and filling; this process is consistent with the actual mining and filling. Different methods of filling with not filling, 20% filling and 50% filling are simulated to the analyze surface settlement in the East district of the Jinshandian Iron Mine. The stability in the below plate is better than in the upper plate, horizontal and vertical displacements are identical in magnitude; and more filling can reduce the settlement of ground surface.
作者 白义如
出处 《三峡大学学报(自然科学版)》 CAS 2013年第1期62-65,共4页 Journal of China Three Gorges University:Natural Sciences
基金 三峡大学博士基金项目(0620070061)
关键词 充填 地表沉降 地下开采 数值计算 filling surface settlement underground mining numerical calculation
  • 相关文献

参考文献5

二级参考文献49

  • 1吴立新,王金庄,赵学胜,李邦三.STRATA AND SURFACE SUBSIDENCE CONTROL IN STRIP-PARTIAL MINING UNDER BUILDINGS[J].Journal of China University of Mining and Technology,1994,4(2):74-85. 被引量:3
  • 2何瑶民,曾卓乔,何凭宗,李洪伟,叶松林,邹峥嵘,罗时恒.立体摄影测量对矿块崩落法引起地表移动的监测研究[J].中南工业大学学报,1995,26(3):305-309. 被引量:2
  • 3王振安.采区上覆岩层下沉机理与规律的研究[J].石家庄铁道学院学报,1995,8(2):42-48. 被引量:3
  • 4Itasc Consulitin Group,Inc.FLAC-3D(Fastlagrangi an Analysis of Continual in 3 Demensions),Version 2.0 User's Manual[M].USA:[s.n.],1997.
  • 5伍鹤皋,生晓高,刘志明.水电站钢筋钢衬混凝土压力管道[M].北京:中国水利水电出版社,2000.
  • 6董哲仁.水电站钢衬钢筋混凝土大型压力管道设计国外概况[A].钢衬钢筋混凝土压力管道文集[C].长江水利委员会信息研究中心,1996.
  • 7Sarkaria G S. Economic Penstock Diameters: a 20-Year Review[J]. Water Power and Dam Construction, 1970. 11.
  • 8Barr D I H. Optimization of Pressure Conduit Sizes[J].Water Power and Dam Construction, 1986.5.
  • 9DL-T5141-200.水电站压力钢管设计规范[s].
  • 10刘宪亮.水电站压力管道的应用、发展与研究[A].第四届全国水电站压力管道学术会议文集[C].郑州:黄河水利出版社,1998.

共引文献69

同被引文献40

引证文献5

二级引证文献19

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部