介绍了某项目深海尾矿排放管道沉管施工方案,着重对沉管过程应力控制进行计算分析,得出控制点参数,并在施工过程中成功应用。
The construction scheme of deep sea tailings discharge pipeline sinking of a project was described briefly, the stress control during pipeline sinking process was calculated and analyzed emphatically, the parameters of the control point were derived and they were successfully applied in the construction process.
出处
《工程建设》
2013年第1期35-37,共3页
Engineering Construction
关键词
深海管道
配重块
沉管
应力
控制点
拉力点
deep sea pipeline
balance weight
pipeline sinking
stress
controlpoint