悬臂施工大跨连续梁桥施工至成桥全过程受力性能分析及设计 被引量:4

Mechanical Property Analyses and Design of Long-span Continuous Girder Bridge from Construction to Completion Constructed by Cantilever Construction Method
下载PDF
导出
摘要 在明确悬臂施工的大跨连续梁桥具体施工过程的基础上,对其进行施工至成桥全过程力学性能分析,以此为基础对其进行详细的设计,进一步明确具体的设计过程和验算内容。结果表明,所设计的桥梁满足相关规范的要求,具有一定的强度和刚度储备。有关经验对同类型的桥梁工程建设和设计具有一定借鉴作用。 Based on the detailed construction process of a long-span continuous girder bridge constructed by cantilever construction method,the mechanical properties are analyzed from construction to completion.Then the bridge is designed in detail,and the design process and the check contents are further clarified.The results show that the designed bridges satisfy the requirements of the guidelines and have the corresponding strength and stiffness margins.The relative experience can be usefully referred for the construction and design of the similar bridge projects.
作者 易泽翰
出处 《城市道桥与防洪》 2013年第2期57-60,6,共4页 Urban Roads Bridges & Flood Control
关键词 连续梁桥 悬臂施工 施工至成桥全过程 受力性能分析 设计 continuous girder bridge,cantilever construction,construction to completion,mechanical property analysis,design
  • 相关文献

参考文献3

  • 1小沃尔特.波多尔尼,J.M.米勒尔.预应力混凝土桥梁分段施工和设计[M].北京:人民交通出版社,1986,1-31.
  • 2JTGD60-2004,公路钢筋混凝土及预应力混凝土桥涵设计规范[S].2004.
  • 3吴刚,万志勇.虎跳门特大桥主桥结构设计[J].城市道桥与防洪,2005(4):43-46. 被引量:2

共引文献3

同被引文献20

引证文献4

二级引证文献6