复杂破碎露天边坡的综合加固技术 被引量:23

Synthetic reinforcement of complicated and broken open pit slope
下载PDF
导出
摘要 为降低剥采比,实现复杂破碎岩体条件下的陡帮开采,针对锦丰露天矿顺层滑坡、楔形体滑坡、倾倒滑坡和松散土体滑坡4种边坡失稳模式,综合考虑露天边坡坡面与岩体层面、岩体质量及边坡重要程度等因素,分别采取喷锚网+长锚索支护、长锚索+钢带支护、喷锚网支护、抗滑桩支护及HDPE防渗膜护坡等方式的大面积边坡加固措施,支护总面积达到53 200 m2,使坡面角达到55°~65°,整体边坡角达到34°~40°,边坡高度超过275 m,实现了复杂破碎深凹露天矿的陡帮开采。结合多年现场实践经验,全面分析了各种边坡加固措施的作用机理、适用范围、技术参数、施工步骤,以及支护效果和优缺点。 In order to carry out steep open pit cutback in Jinfeng, which has a very complicated and broken rock condition, and at the same time decrease the stripping ratio, a study of its four main failure mechanism, namely, planar, wedge, toppling and sliding was conducted, giving fully consideration to factors likes of batter angle, rock bedding, rockmass quality and crucial priorities of batter in different domains. The slope supporting methods are as follows: mesh+split sets+shotcrete+cable bolts, cable bolts + mesh stripe, mesh+shotcrete+split sets, sheer pins and high density polyethylene (HDPE) membranes, total reinforement area reaches 53 200 m2, which enables successful cutback mining with the face angle at 55°-65°, overall angle of wall at 34°-40°, the maximal height of slope with 275 m. Based on years of practice and experience, a comprehensive analysis of action mechanism of above mentioned reinforcement methods, their application scope, technical parameters and implementation procedures, as well as the effect, pros and cons of these methods are presented.
出处 《中南大学学报(自然科学版)》 EI CAS CSCD 北大核心 2013年第2期772-777,共6页 Journal of Central South University:Science and Technology
基金 国家"十二五"科技支撑计划项目(2012BAB08B02) 国家自然科学基金资助项目(50934002)
关键词 复杂破碎岩体 露天边坡 边坡破坏模式 综合加固 complicated and broken rock mass open pit slope failure mechanism of slope synthetic reinforcement
  • 相关文献

参考文献17

  • 1张四维.我国露天矿边坡工程研究成果与进展[J].地质灾害与环境保护,2000,11(2):98-101. 被引量:19
  • 2Abbas T, Kazuo T. Assessment of the stability of rock slopes by the slope stability rating classification system [J]. Rock Mechanics and Rock Engineering, 2010, 43(3): 321-333.
  • 3Mohsen A, Kourosh S, Mostafa S. Uncertainty and reliability analysis applied to slope stability: A case study from Sungun copper sine[J]. Geotechnical and Geological Engineering, 2011, 29(4): 581-596.
  • 4Gali M L, Arunakumari G. Seismic stability analysis of a fimalayan rock slope[J]. Rock Mechanics and Rock Engineering, 2010, 43(6): 831-843.
  • 5Fehmi A, Fatih Y, Sureyya S, et al. Geotechnical assessments of the stability of slopes at the Cakmakkaya and Damar open pit mines (Turkey): A case study[J]. Environmental Earth Sciences, 2010, 61(4): 741-755.
  • 6Bagdasar A G, Lukishov B G, Rodionov V N, et al. Detection of features of a rupture structure in walls of an open pit in terms of the Muruntau open pit[J]. Journal of Mining Science, 2008, 44(1): 73-81.
  • 7Adhikary D P, Dyskin A V. Modeling Of progressive and instantaneous failures of foliated rock slopes[J]. Rock Mechanics and Rock Engineering, 2007, 40(4): 349-362.
  • 8Jhanwar J C, Thote N R. Slope failures in the Opencast Coal Mines of Wardha valley coalfield in central India[J]. Rock Mechanics and Rock Engineering, 2011, 44(5): 635-640.
  • 9Chanyshev A I, Efimenko L L. Estimate of the stability of stratified slopes based on the plastic theory[J]. Journal of Mining Science, 2007, 43(4): 382-393.
  • 10Donnelly L J, Culshaw M G, Hobbs P R N. Engineering geological and geophysical investigations of a slope failure at Edinburgh Castle, Scotland[J]. Bulletin of Engineering Geology and the Environment, 2005, 64(2): 119-137.

二级参考文献45

共引文献91

同被引文献174

引证文献23

二级引证文献114

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部