摘要
以某供水隧洞1号支洞上游通风设计为例进行了通风量的计算,结合总体施工进度安排,选定通风设备,优化通风方案。
Taking the design of a diversion tunnel’s ventilation through its No.1 access tunnel in construction period as an example,the paper presents the calculation of air ventilation amount,combining with the project’s general construction progress,selects the ventilation equipment and optimizes the ventilation scheme.
出处
《山西水利科技》
2013年第1期23-24,38,共3页
Shanxi Hydrotechnics
关键词
通风方案
风量
风压
设备选型
ventilation scheme
air amount
air pressure
selecting equipment model