场地平整施工参数的确定直接影响平整施工的技术和经济性,主要利用最小二乘法进行竖向规划设计,采用四方棱柱体法计算平整土方量,选用表上作业法确定最优的土方调配方案,通过这些方法的综合使用,以便在实际综合厂区和场站工程场地平整施工中加以应用。
The determination of ground leveling construction parameters directly affected the technical and economic of leveling construction, mainly used least square method to make vertical planning design, used the tetragonal prism method calculation of earthwork quantity, selection of operating table to determine the optimization earthwork allocation scheme, through the comprehensive using of these methods, applied to the actual comprehensive plant and site leveling construction.
出处
《山西建筑》
2013年第10期108-109,共2页
Shanxi Architecture
关键词
最佳设计平面
场地平整
压实程序
土方调配
optimization design plane, ground leveling, compaction procedure, earthwork allocation