摘要
介绍某电厂2号1 000MW发电机组保护动作跳闸事故的经过,通过分析故障录波波形、保护动作和现场检查情况,认为发电机出线小室异物引起定子内部发生三相短路是事故的主要原因,并提出处理措施及建议。
This paper shows the process of a generator shortcircuit fault, analyzes the waveform of the memory equipment, the action of protection equipment, together With the check on site,considers that the main reason is generator line secondary room eyewinker leading to three phase short-circuit,also descripts the settlement and suggestions.
出处
《河北电力技术》
2013年第1期31-33,共3页
Hebei Electric Power
关键词
发电机
三相短路
保护动作
故障点
generator
three-phase short-circuit
protection pick-up
failure point