摘要
简单介绍邯钢西区(邯宝公司)炼铁厂1号、2号高炉的热风炉系统,对原有的热风炉煤气、空气双预热系统在应用中存在的问题及原因进行分析。生产实践表明,通过采取相应的措施对此双预热器进行改进与创新,取得了明显效果,满足了生产要求。
To introduce briefly the hot blast stere system of No.1 and No.2 blast furnace in Han gang western Iron works.To analyze the problems in the application of the original stove gas and air preheating system as well as its causes.The production indicates that it achieves remarkable effect and meets production requirement by improving the double preheater.
出处
《山西冶金》
CAS
2013年第1期69-70,共2页
Shanxi Metallurgy
关键词
热风炉
余热回收
双预热
串联
并联
hot stove
waste heat recovery
double preheating
series
parallel