摘要
重点论述了高压并联电抗器在减少阳城发输电系统线路的工频过电压、电能损耗和提高输电线路重合闸成功率方面所起到的作用,介绍了阳城电厂高压并联电抗器的结构,分析了高压并联电抗器投运后出现的问题,提出了改进措施。
This paper emphatically discusses the functions of high voltage parallel reactor in aspects oi reducing me power frequency overvohage and electric energy loss and improving the reclosing success rate of transmission line in Yangcheng Power Generation And Transmission System, and introduces the structure of high voltage parallel reactor of Yangcheng Power Plant, expounds some problems occurring after the high voltage parallel reactor was put into operation, and puts forward some improvement measures.