摘要
针对通霍扩能改造工程双泡子站场改造工程,提出施工封锁方案,并从安全、合理化、工期等方面对各个方案进行了研究,通过优化施工过渡方案,使得施工与运输互不干涉,既满足了施工要求,又满足了运输要求。
In light of Shuangpaozi station yard transformation engineering of Tong-Huo energy expansion transformation project,the paper puts forward construction blocking scheme,and studies various schemes from aspects of safety,rationality and construction duration.Through optimizing construction transition scheme,it guarantees normal transportation during the construction period,which not only meets construction demand,but also meets transportation demand.
出处
《山西建筑》
2013年第8期129-130,共2页
Shanxi Architecture
关键词
车站
站场改造
施工方案
优化
station
station yard transformation
construction scheme
optimization