摘要
介绍T形梁预制采用手摇棘爪整体立拆模系统和配套的整体钢筋笼绑扎系统的施工工艺,从整体绑扎台座及其钢筋绑扎、安装及整体模板立拆模作业工序等方面进行阐述,可为以后在进行T梁预制施工时提供借鉴。
This paper introduces the T beam prefabrication with construction process of hand pawl overall vertical stripping system and the overall supporting reinforcement cage lashing system from the perspectives of overall binding pedestal and reinforcement, installation and overall template vertical stripping operation process and other aspects to provide reference for the T girder prefabrication construction.
出处
《铁道建筑技术》
2013年第3期81-83,共3页
Railway Construction Technology
关键词
T梁预制
钢筋笼
模板
T beam prefabricate
steel cage
template