摘要
总结了福州市二环路象山公路四联拱隧道在大跨、浅埋、偏压、软岩条件下 ,采用“墙洞法”施工 ,运用控制爆破、量测监控等技术 ,解决了施工中结构受力转换、涌水。
It summarized the construction of the four arc tunnel of Xiangshan Highway of Fuzhou City under the condition of big span ,shallow burried bia pressed and soft rock, which adopted the 'wall care method' and applied the controlled blasting and measurement supervision technology . It solved the problems of stress changing of structure, water emerging and collapse deformation during the construction.
出处
《西部探矿工程》
CAS
2000年第3期51-52,共2页
West-China Exploration Engineering
关键词
四联拱隧道
设计
施工
four arc tunnel design construction