项目进度绩效预测研究——基于挣得技术的三种进度预测方法比较分析 被引量:2

Research on Project Schedule Performance Prediction:A Comparative Analysis of Three Earned Value Methods
原文传递
导出
摘要 对项目进度绩效预测方法进行比较分析。首先描述六种项目状态下项目进度预测问题,系统阐述计划价值率法、挣得工期法和挣得进度法的进度预测方法。结合某工程建设项目案例,对三种方法的进度预测结果进行分析:在项目早、中期,三种方法预测结果差异不明显,但在项目接近收尾阶段,挣得进度法更能准确反映项目未来的进度状态。 This paper aims to make a comparative analysis of different methods for project schedule performance prediction. Firstly, the schedule performance prediction problem in the six statues is described. The plan valued rate method, earned duration method and the earned schedule method are then introduced. At the end of this paper, an engineering construction project is used to make compare. The result shows that three methods made no differ- ences result before middle stage. But the earned schedule method progressed more accurately future forecast in the end of the project.
出处 《建筑经济》 北大核心 2013年第4期19-22,共4页 Construction Economy
基金 863高技术研究和发展计划资助项目(KX07301)
关键词 预测 挣得技术 计划价值率 挣得工期 挣得进度 prediction earned value method plan value rate earned duration earned schedule
  • 相关文献

参考文献6

  • 1Anbari F. T. Earned value method and extensions [J]. Project Management Journal, 2003,34 (4) : 12-19.
  • 2Walt Lipke,Ofer Zwikael,Kym Henderson,etc. Prediction of projeet outcome: the application of statistical methods to earned value management and earned schedule performa- nce indexes[J].International Journal of Project Management, 2009 (27) .. 400-407.
  • 3Jacob D. Forecasting project schedule completion with earned value metrics [J].The Measurable News,2003, spring(l ) :7-9.
  • 4Jacob D. S.,Kane M. Forecasting schedule completion using earned value metrics revisited [J]. The Measurable News, 2004, summer( 1 ) : 11-17.
  • 5Henderson K. Further developments in earned schedule[J]. The Measurable News 2004, Spring: 15-16 ; 20-22.
  • 6高朋,冯俊文,王华亭.基于时间EVT的项目进度预测方法[J].系统工程,2009,27(12):100-104. 被引量:6

二级参考文献7

  • 1Project Management Institute. A guide to the project management body of knowledge (4th edition)[Z]. Newtown Square, PA: Project Management Institute, 2008.
  • 2Lipke W, et al. Prediction of project outcome the application of statistical methods to earned value management and earned schedule performance indexes[J]. International Journal of Project Management, 2009,27 : 400-407.
  • 3Fleming Q W, Koppelman J M. Earned value project management (3rd Ed. ) [Z]. Newtown Square, PA : Project Management Institute ,Inc. ,2006.
  • 4Anbari F T. Earned value method and extensions [J]. Project Management Journal, 2003,34 (4) : 12.
  • 5Jacob D. Forecasting project schedule completion with earned value metrics[J]. The Measurable News, 2003, (March) : 7 - 9.
  • 6Jacob D S, Kane M. Forecasting schedule completion using earned value metrics revisited[J]. The Measurable News,2004, (Summer) : 7-11.
  • 7戚安邦.多要素项目集成管理方法研究[J].南开管理评论,2002,5(6):70-75. 被引量:116

共引文献5

同被引文献5

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部