摘要
通过分析尼日利亚阿卡铁路项目实际发生的两起合同验工条款索赔和两个优化设计变更的成功案例,总结合同索赔和设计变更的过程和取得的成果,分析总价合同和单价合同采用不同的处理方式,阐述合同索赔和设计变更时与咨询工程师或业主谈判的技巧,最后提出索赔和变更取得成功的重要条件,即紧抓合同,实现互利共赢。
Based on the successful cases-two claims for the contract clauses of the measurement of work executed and two design variations optimization actually occurred in the summarizes the process and aceomplishments of contract claims Nige and rian Railway Modernization Project, this paper design variations, analyzes the different treat- ments adopted for both lump-sum contract and unit price contract; states the negotiation skills for the project's era- ployer or the consultant regarding to the contract claims anti design variations. At last, the important conditions of the success for the claims and variations are put forward -basing on the contract tight to occupy the commanding point of the theory, following the strategy of mutual benefit and win-win results to create better benefit for the project.
出处
《建筑经济》
北大核心
2013年第4期38-41,共4页
Construction Economy
关键词
国际工程
合同索赔
变更优化
international project
claim
design variation