复杂地质条件下高层建筑刚性桩复合地基应用与研究 被引量:3

Application and study on the rigid pile composite foundation for high-rise buildings under complicated geological conditions
原文传递
导出
摘要 某高层办公楼建造场地地质分布极不均匀,存在软弱土、岩体破碎带等不良地质条件,采用天然地基与常规桩基均不合适。经方案比选,采用刚性桩复合地基,结合桩间土注浆、桩底后注浆的综合性地基处理方案,可满足承载要求。针对因施工质量原因,实际桩长远小于设计要求,从而造成单桩竖向承载力检测不合格,并导致复合压板静载试验结果未能满足承载力要求的状况,根据现场施工条件,提出通过人工套挖置换成桩,构造二元刚性桩复合地基的解决方案。加固措施实施效果良好,实测沉降远小于规范限值。采用的地基处理方案针对性较强,工程事故处理方法实用性较好。 The geological distribution is very uneven in a high-rise office building construction site and there are adverse geological conditions,such as soft soil,rock fracture zone,and so on,so both the natural foundation and the pile foundation are not suitable.Along with the comprehensive foundation treatment measures of pile post-grouting and grouting in the soil among piles,a rigid pile composite foundation that can meet the bearing requirement was applied after comparison of foundation schemes.Owing to the poor quality of construction,the actual pile length was far below the design demand,which leaded to failure detection on vertical bearing capacity test of single pile and composite platen static load foundation.In view of the fact that the test results failed to reach the design requirements,and based on construction site conditions,the solution method of building dual-element rigid pile composite foundation by replacing some rigid piles with manual hole digging piles was proposed.Reinforcement measures have good results,and the measured settlement is far less than the code limit.The foundation treatment method is highly targeted,and the measures of engineering accident treatment have good practicality.
出处 《建筑结构》 CSCD 北大核心 2013年第6期86-91,共6页 Building Structure
基金 国家科技支撑计划(2011BAG07B01)
关键词 复杂地质条件 高层建筑 刚性桩复合地基 工程事故处理 complicated geological condition high-rise building rigid pile composite foundation engineering accident treatment
  • 相关文献

参考文献9

二级参考文献34

  • 1宰金珉.桩土明确分担荷载的复合桩基及其设计方法[J].建筑结构学报,1995,16(4):66-74. 被引量:134
  • 2龚晓南.地基处理技术与复合地基理论[J].浙江建筑,1996(1):35-37. 被引量:4
  • 3阎明礼,吴春林,杨军.水泥粉煤灰碎石桩复合地基试验研究[J].岩土工程学报,1996,18(2):55-62. 被引量:67
  • 4龚晓南 杨灿文.综合报告(五),地基处理.第六届土力学及基础工程学术会议论文集[M].上海:同济大学出版社,1991..
  • 5.JGJ79-91.建筑地基处理技术规范(修订稿)[S].,..
  • 6中国船泊工业总公司第九设计院.弹性地基梁及矩形板计算[M].北京:国防工业出版社,1983..
  • 7沈球.理论土力学[M].北京:中国水利水电出版社,2000..
  • 8刁学优 鲍自均 程家铭 等.某高层办公楼(10层)套箱基础-框架体系协同作用的测试研究[J].建筑结构学报,1988,(5):62-70.
  • 9刁学优 鲍自均 程家铭 等.某高层办公楼(10层)套箱基础一框架体系协同作用的测试研究[J].建筑结构学报,1988,(5):62-70.
  • 10黄绍铭,王迪民,裴杰,等.减少沉降量控制桩基的设计与初步实践[C]//第六届全国土力学基础工程学术会议论文集.北京:中国建筑工业出版社、上海:同济大学出版社,1991.

共引文献341

同被引文献28

引证文献3

二级引证文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部