摘要
科威特中央银行新总部大楼高约239m,由主楼、裙楼和人防工程组成。部分区域采用清水砖墙作为围护结构。详细介绍了清水砖墙的施工过程及质量控制措施,包括砂浆的配合比设计、灰缝的饱满度以及节点设计。同时,清水砌体砌筑过程中还涉及与其他专业协调工作。通过加强施工过程管理,保证了清水砌体的顺利施工。
The new headquarters office building for Central Bank of Kuwait is about 239m high,consisting of office tower,podium and shelter.Part of the building uses fair-faced brick wall as the enclosure structure.This paper introduces in detail the construction procedure and quality control measures for the fair-faced brick wall including mix proportion design of mortar,richness of mortar seam and joint design.Wall construction involves coordination with other disciplines.By strengthening construction process management,the construction of the fair-faced brick wall is completed successfully.