泥质砂岩地质条件下非爆破顶管施工技术及其对邻近构筑物的影响 被引量:6

Non-blasting Pipe Jacking Construction in Muddy Sandstone Region and Its Influence on Adjacent Structures
下载PDF
导出
摘要 南京南站某变送电线路电缆隧道工程采用顶管法施工,周围构筑物较多。介绍了工程存在的难点,然后分别详细介绍了手掘式顶管与机械式顶管的施工工艺,并对控制土体变形及穿越河道时防透水的措施进行了介绍。最后根据监测数据对邻近构筑物的影响进行了分析。监测数据表明,顶管施工未对邻近构筑物造成显著影响,确保了工程及邻近构筑物的安全。 Pipe jacking construction technology was adopted in the construction of a cable tunnel of the transmission line for Nanjing South Station, and along the line, there are many buildings nearby. The construction difficulties were firstly discussed. After that, the construction technologies of manual pipe jacking and mechanical pipe jacking were introduced in detail. Some measures were also introduced to control the soil deformation and prevent flooding during pipe jacking across the river. At last, the effect of the construction on adjacent structures was analyzed in detail based on the monitoring data, which shows that pipe jacking construction caused no significant influence on the neighboring structures.
出处 《施工技术》 CAS 北大核心 2013年第7期58-62,共5页 Construction Technology
基金 中冶天工上海十三冶基础工程分公司科研专项基金资助(2011-JCKY-1)
关键词 地下工程 泥质砂岩 顶管 非爆破 监测 变形 施工技术 underground deformation construction muddy sandstone pipe jacking non-blasting monitoring
  • 相关文献

参考文献4

  • 1中国地质大学(武汉).顶管施工技术及验收规范(试行)[S].北京:中国非开挖技术协会,2012.
  • 2GB50497-2009建筑基坑工程监测技术规范[S].北京:中国计划出版社.2009.
  • 3上海铁路局高速铁路运营期路桥沉降观测管理方法[S].上海:上海铁路局,2011.
  • 4建筑施工手册(4版)[M].北京:中国建筑工业出版社,2003.

共引文献164

同被引文献25

引证文献6

二级引证文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部