介绍了AP1000核电厂蒸汽发生器排污系统的主要系统流程和系统功能,简述了该系统在常规岛内的主要布置要求和布置特点,可为设计人员熟悉本系统和进行布置设计提供一定的参考。
The main system procedure and system function of steam generator blowdown system in CI-building of AP1000 nuclear plant are described. The disposal requirements and characteristic are discussed. The opinions can be used as reference for the designers to acknowledge the system and make the disposal.