蒙西超大直径立井临时改绞混合提升新技术 被引量:3

The New Mixed Hoisting Technology for the Large Diameter Vertical Shaft Temporary Winding Change in Western Inner Mongolia
下载PDF
导出
摘要 在矿井建设中,临时改绞是必不可少的环节,井筒到底后通过临时改绞可以在较短的时间内形成较大的提升能力,能够加快矿井建设速度。传统立井临时改绞后,提升方式为矿车运输和临时罐笼提升相组合的运输方式。新改绞工艺增加了箕斗提升系统,采用了双罐笼和双箕斗的混合提升方式,并且在井底增设了临时煤仓和半自动装煤系统。实现了矸石提升和物料、人员运输的分离,并且用胶带运输替代矿车运送矸石,极大提高了整个立井临时提升系统的提升效率。 In mine construction, temporary winding change is necessary link twisted, shaft by temporarily winding change after exactly ground can be in relatively short time form bigger promotion ability, can speed up the mine construction speed. Traditional shaft temporary winding change, ways to upgrade for harvesters transportation and temporary cage combined promotion modes of transport. New winding change process increases the skip upgrade system, and coal bunker in the bottom of the shaft and additional temporary semi-automatic coal loading system, using a double the cage and double skip mixed ways to upgrade. It realizes transportation of separation for coal wasting promotion, materials and personnel promotion, and use belt conveyor substitute for tape transportation shipping coal wasting, greatly improving the system of vertical shaft temporary promotion efficiency.
出处 《价值工程》 2013年第11期71-73,共3页 Value Engineering
关键词 临时改绞 混合提升 箕斗 罐笼 立井 提升 temporary winding change mixed hoisting skip cage shaft promotion
  • 相关文献

参考文献8

二级参考文献8

共引文献31

同被引文献9

引证文献3

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部