摘要 界河金矿4号矿体属于矿岩很破碎、极易冒落、金属品位高的难采矿体。以往矿山用上向水平分层废石充填法开采时,在安全、资源回收上存在较大问题。因而改用下向胶结充填法。首先进行试验回采,完善回采工艺后再全面推广应用。试验中采用了预埋钢筒形成充填小井的新方法,首创工艺简单实用的充填接顶指示装置。由于使用下向胶结充填法,提高了回采安全性及资源回收率,使损失率降至8%,贫化率降至5%。 No.4 orebody of Jiehe Gold Mine is one of very broken, easy roof-falling and high in metal value. Originally, overhand out-and-waste fill stoping with waste filling was used, resulting in serious problems in safety and metal recovery rate. Therefore, it was replaced by underhand cut-and-cemnted-fill mining method after experiments were done in a trial stope. In the test, a steel tube was pre-buried to form a small filling well and a simple but useful fill-packed roof indicator was designed. Thanks to the change of mining method, safety was greatly improved and metal recovery rate was increased so as to reduce loss rete to 8% and dilution rate to 5%.
作者 胡修章
机构地区 长沙矿山研究院
出处 《长沙矿山研究院季刊》 北大核心 1991年第2期21-26,共6页
关键词 金矿 采矿 下向充填法 胶结充填法 Gold mining, Cemented fill mining, Underhand cut-and- fill stoping, Recovery rate
  • 相关文献

同被引文献3

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部