地铁35kV供电分区设置分析

Analysis of 35 kV Metro Power Supply Section Numbers
下载PDF
导出
摘要 目前国内地铁35kV环网过流保护的时间级差按0.30s配置,无法保证过流保护的选择性。提出通过缩减过流级差配合时间的方案,来解决地铁35kV供电分区过流保护的选择性问题,同时分析了一个供电分区内变电所设置数量对投资的影响。在不改变主变电所过流时间配合的情况下,正线变电所过流时间级差配合为0.25s或0.20s,且一个供电分区内变电所设置数量不超过4座为宜。 The current 35 kV metro power supply section cannot solve the selective problem for overcurrent protec tion because the stage difference coordination is fixed at 0. 30s, a new method is proposed in this article that will re duce the time of stage difference coordination. At the same time, the influence over investment by the number of sub station allocated in one power supply section is analyzed. It is suggested that the stage difference coordination of the main substation overcurrent protection should be kept be tween O. 25 s and O. 20 s, the number of substation allocated in one power supply section should be limited to 4.
作者 王明飞
出处 《城市轨道交通研究》 北大核心 2013年第4期58-60,共3页 Urban Mass Transit
关键词 地铁 供电分区 过流保护 变电所 级差配合 metro power supply section over-current pro-tection substation stage difference coordination
  • 相关文献

参考文献2

  • 1中铁二院工程集团有限责任公司.深圳地铁龙岗线首期工程供电系统35kV继电保护整定单[G].成都:中铁二院工程集团有限责任公司,2011.
  • 2江苏上上电缆集团.深圳地铁龙岗线首期工程没计联络资料[G].成都:中铁二院工程集团有限责任公司,2008.

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部