摘要
PC连续梁桥常采用悬臂浇注的方法施工。由于受各种因素的影响,使其节段施工的周期会存在一定差异,从而影响成桥后梁体的徐变效应。本文结合一座铁路连续梁桥的施工过程,通过有限元建模分析探讨了悬臂施工节段的施工周期对连续梁桥成桥后徐变效应的影响,得出对于连续梁施工具有参考意义的几点结论。
Prestressed concrete continuous beam bridge often adopt cantilever casting method. As the result of many factors, the segmental construction cycle will be difference, thus affecting the bridge girder creep effect. Combination of two railway continuous beam bridge construction process, through the finite element modeling of cantilever segmental construction of continuous beam with different construction period analysis creep effect after the bridge finished, then some meaningful conclusions for the construction of continuous beam are drawn.
出处
《科技信息》
2013年第5期64-65,共2页
Science & Technology Information
关键词
连续梁桥
悬臂施工
施工周期
徐变效应
Continuous beam bridge
Cantilever construction
Cycle
Creep