埃塞俄比亚ADAMA风电工程风机吊装进度的主要影响因素及对策综述 被引量:2

Summary of Major Factors Affecting Progress of WTG Installation and Countermeasures,Adama Wind Farm Project, Ethiopia
下载PDF
导出
摘要 总结了埃塞俄比亚ADAMA风电项目风机吊装施工进度的主要影响因素,如:风速、机位间道路、物流、货损的修复进度等,并提出了相应解决措施。在国外工程实践中,合理控制了工期,有效降低了工程成本,取得了良好效果。 the major factors affecting progress of WTG installation and , Adama wind farm project, Ethiopia, are summa- rized such as wind speed, access between WTGs, logistics, remedy progress of goods damage, etc. the corresponding countermeasures are raised. In the overseas engineering practice, the construction period is controlled reasonably, cost reduced effectively and expected effect achieved accordingly.
作者 冯俊海
出处 《西北水电》 2013年第2期75-77,共3页 Northwest Hydropower
关键词 风机 吊装 影响因素 解决措施 埃塞俄比亚 WTG lifting and installation affecting factor countermeasures Ethiopia
  • 相关文献

参考文献3

  • 1金风科技股份有限公司.金风1500kW系列风力发电机组安装手册-D版[S].2010,12.
  • 2DL/T19568-2004,风力发电机组装配和安装规范[S].北京:中国标准出版社.2004.
  • 3Hydrochina Corporation. Feasibility study for Ethiopian Adama ( N azret ) wind park [ R ]. 2009,11.

同被引文献19

  • 1GB/T50358-2005建设项目工程总承包管理规范[S].北京:中华人民共和国建设部,2005.
  • 2唐扬文,李建友.龙滩水电站水轮机埋件运输及吊装[J].水电站机电技术,2007,30(4):53-55. 被引量:2
  • 3全国一级建造师执业资格考试用书编写委员会.建设工程经济[M].4版.北京:中国建筑工业出版社,2011.
  • 4NB/T31011-2011,陆上风电场工程设计概算编制规定及费用标准[S].北京:中国电力出版社,2011.
  • 5GB/T19568-2004,风力发电机组装配和安装规范[S].北京:中国标准出版社,2004.
  • 6Q/JF2S/1500SM.7-2008.金风1500 k W系列风力发电机组安装手册[S].B0版.新疆:金凤科技有限公司,2010,12.
  • 7中华人民共和国海关进出口税则编委会.中华人民共和国海关进出口税则及申报指南[S].2013.
  • 8全国建筑施工企业项目经理培训教材编写委员会.施工项目成本管理[M].北京:化学工业出版社,2010.
  • 9吴迪,林远山,王欣,王秀坤.面向吊装方案演示的履带起重机仿真系统设计[J].系统仿真学报,2008,20(5):1187-1191. 被引量:18
  • 10张延锋,罗斌,张继成.轴流转桨式水轮机转轮整体吊装的方法和特点[J].西北水电,2008(2):45-48. 被引量:4

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部