116MW循环流化床热水锅炉调试技术探讨

The Discussion of the Hot-water Boiler Commissioning Techniques for the 116 MW Circulating Fluidized Bed
下载PDF
导出
摘要 阐述了某热源厂116 MW循环流化床热水锅炉的结构特点,制定了适合流化床热水锅炉启动调试过程中的煮炉方案,分析了热水锅炉频繁启停以及带负荷试运阶段锅炉出水压力波动大等原因,为循环流化床热水锅炉调试及运行提出了建议。 This article states the structural characteristics of the 116 MW circulating fluidized bed's hot-water boiler of one heat source plant, and then makes the boiling-out plan suitable for the hot-water boiler of the circulating fluidized bed to start up its commissioning process. After analyzing the causes for the hot-water boiler's frequent shutdown and the fluctuating discharge pressure during the on-load trial operation, this article also proposes suggestions for the commissioning and operation of the circulating fluidized bed's hot-water boiler.
出处 《山西电力》 2013年第2期48-51,共4页 Shanxi Electric Power
关键词 循环流化床 热水锅炉 调试 circulating fluidized bed hot-water boiler commissioning
  • 相关文献

参考文献2

二级参考文献3

  • 1张传聚.热水锅炉原理与设计[M].济南:山东科学技术出版社,..
  • 2吴竹平,1995年
  • 3杨励丹,电工信息与建议,1991年

共引文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部