摘要
以京石高铁某(32.6+48+32.6)m连续梁施工为例,根据脚手架和贝雷架的受力特性,对其进行了施工前的计算分析,并对支架的计算结果提出建议,进而得到了一些有益的结论。
Taking the(32.6+48+32.6)m continuous beam construction of Jing-Shi express railway as an example,according to the mechanical features of scaffold and assemble steel bridge truss,the paper carries out calculation analysis before construction,and puts forward some suggestions for support calculation results.Furthermore,it has obtained some beneficial conclusions.
出处
《山西建筑》
2013年第13期176-177,共2页
Shanxi Architecture
关键词
连续梁
脚手架
贝雷架
continuous beam
scaffold
assembled steel bridge truss