摘要 文章以坝陵河大桥为研究对象,建立了全桥施工过程空间非线性分析模型,并采用全刚结法及有铰逐次刚结法两种加劲梁施工方案进行了施工全过程的模拟仿真计算,研究了不同加劲梁方案下大桥结构受力状态及钢桁加劲梁安装阶段临时架设铰的作用,确定了合理的钢桁加劲梁施工方案。 With Baling River Bridge as the research object,the article established the spatial nonlinear analysis model of bridge construction process,and used two stiffening girder cor struction plans of rigid structure method and hinge successive rigid structure method to conduct the simulation calculations of the whole construction process, studied the bridge structure stress state under the different stiffening girder programs and the role of temporary hinge erection during steel-truss stiffening girder installation stage, and determined the reasonable steel-truss stiffening girder construction program.
作者 方守波
出处 《西部交通科技》 2013年第3期28-34,共7页 Western China Communications Science & Technology
关键词 悬索桥 钢桁架加劲梁刚结法 施工方案 Suspension bridge Steel-truss stiffening girder Rigid structure method Co-nstruction program
  • 相关文献

参考文献3

二级参考文献3

  • 1沈锐利 廖海黎.悬索桥静动力空间非线性计算有限元模型及其应用[A]..全国桥梁结构学术大会论文集[C].上海:同济大学出版社,1992.935-940.
  • 2潘世建,杨盛福.厦门海沧大桥建设丛书[M].第二册.北京:人民交通出版社,2002.193~193
  • 3唐茂林,沈锐利,强士中.大跨度悬索桥非线性静动力分析与软件开发[J].桥梁建设,2000,30(1):9-12. 被引量:15

共引文献23

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部