摘要 为保证安装后的接触线高度符合设计要求,需在接触网施工过程的各个环节严格控制整体吊弦的预配精度,为此,从整体吊弦预配计算中接触悬挂的建模方法、接触网术语的界定、测量和预制过程四方面分析了造成吊弦预配误差的成因,并提出了解决措施。 In order to ensure the standard height of contact wire, the integral droppers's pre-assigned accuracy must be strictly controlled during the whole procedures of construction process of OCS( Overall Contact system). This article discussed four causes of dropper pre-distribution error and provided corresponding solutions in these aspects including modeling method of OCS in overall dropper pre-distribution calculation, accurate definition of OCS terminology, calculation process control and prefabrication process control.
作者 刘道良
出处 《中国西部科技》 2013年第5期17-18,共2页 Science and Technology of West China
关键词 接触悬挂 整体吊弦 预配误差 Contact suspension Integral droppers Pre-distribution error
  • 相关文献

参考文献12

二级参考文献4

  • 1[2]吴耀庭.铁路曲线及其养护[M].北京:中国铁道出版社,2004.
  • 2[7]中铁建电气化局集团公司.电气化铁路接触网综合施工技术鉴定文件[R].北京:中铁建电气化局,2004.
  • 3邢尊军.高速接触网整体吊弦及导线高度误差控制[A]..高速铁路牵引供电技术研究[C].北京:中国铁道出版社,1995..
  • 4中国铁路工程总公司教卫处组织.接触网工[M]中国铁道出版社,1999.

共引文献27

同被引文献7

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部