期刊文献+

AP1000电站保护和安全监控系统预运行测试分析 被引量:3

Analysis on pre-operational test of protection and safety monitoring system of AP1000 nuclear power plant
下载PDF
导出
摘要 在AP1000电站中,保护和安全监控系统是基于Common Q平台设计的安全级仪控系统。为确保电站运行前保护和安全监控系统满足系统设计功能要求,采用交叠测试方法对保护和安全监控系统进行了预运行测试。结合保护和安全监控系统的结构和功能,对保护和安全监控系统预运行测试进行介绍和分析,供预运行测试时参考。 In the AP1000 nuclear power plant,the protection and safety monitoring system(PMS) is a safety I&C system,which is designed based on the Common Q platform.Before the plant is put into operation,in order to ensure the PMS can satisfy the designed system function requirement,using the over-lap test method,the PMS pre-operational test was carried out.Combining with the structure and function of PMS,the PMS pre-operational test was introduced and analyzed in this paper,which can be used as reference for pre-operational test.
作者 张思成 许江
出处 《华电技术》 CAS 2013年第4期72-75,79,共4页 HUADIAN TECHNOLOGY
关键词 AP1000电站 保护和安全监控系统 预运行测试 交叠测试 分析 AP1000 nuclear power plant protection and safety monitoring system(PMS) pre-operational test over-lap test analysis
  • 相关文献

参考文献1

  • 1中国核工业集团公司.APl000核电厂系统与设备[M].北京:原子能出版社,2010:132-155.

共引文献4

同被引文献2

引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部