本文介绍了云南至广东±800kV特高压直流输电工程换流站主设备监造的范围和特点,对换流站主设备的设计、制造和服务承诺等阶段的监造控制作了较为详细的论述,总结了云广工程设备监造的主要经验,以及需要重点关注的问题。
This article introduced the scope and supervision at the converter station of Yunnan characteristics of main equipment manufacturing to Guangdong ± 800kV UHVDC Transmission Project. With detailed discussions on the supervision and control during the main equipment design, manufacturing and service process, this article summarized experience and learning of the Yunnan to Guangdong Transmission Project and raised attention to some problems. And the detailed representation has described for the main equipment quality assurance during the design, manufacture and service promise. The equipment manufacture and supervision experience has concluded and the main course should be focused on in the following projects.
出处
《设备监理》
2013年第3期53-56,共4页
Plant Engineering Consultants
关键词
直流工程
换流站
设备监造
品质保障
Direct Current (DC) project, converter station, plant engineering consulting service,quality assurance.