摘要
以云南呈贡东外环中路工程的路基填方工程为背景,选择三处高填方段进行现场的填筑实验,同时对实验工艺进行了相关的介绍,对实验过程进行相关的说明,结合不同填料的填筑的实验情况,分析了填筑厚度、施工机械及工艺对填筑效果的影响,以供同类工程参考。
A trial test program involves the testing of high fill embankment construction techniques at three locations of the Kunming Outer-Loop Project. This paper summarizes the embankment construction techniques with different fill materials. The embankment performances resulted from the different fill lift thicknesses; compaction equipment and the compaction technique are presented.
出处
《土工基础》
2013年第2期21-24,29,共5页
Soil Engineering and Foundation
关键词
路基
加固
实验
Embankments
Soil Improvement
Trial Tests