摘要
基工程基础后浇带设置较多,施工不当易引发裂缝、渗漏水等问题。施工中通过优化后浇带封闭方法,采用快易收口网将后浇带两侧封闭,混凝土无渗漏;改进支撑方法,后浇带两侧梁板受力稳定均衡,有效控制沉降,保证了后浇带的整体性,保障了后浇带的施工质量。
There are many post-pouting concrete belts in the foundation of Guomai Building project and improper construction may easily cause cracks and water leakage. During construction, post-pouring belt blocking method is optimized and high ribbed formwork is used to block both sides of post-pouring belt and successfully prevent concrete leakage; supporting method is improved to realize stable and balanced forces on both sides of beam slab, effectively control settlement and ensure the integrity and construction quality of post- pouring belt.
出处
《建筑技术》
2013年第5期460-462,共3页
Architecture Technology
关键词
后浇带
混凝土
收口网
支撑
post-pouring belt
concrete
high ribbed formwork
support