国脉大楼工程后浇带支模施工技术 被引量:2

FORMWORK CONSTRUCTION TECHNIQUE FOR POST-POURING CONCRETE BELT IN GUOMAI BUILDING PROJECT
下载PDF
导出
摘要 基工程基础后浇带设置较多,施工不当易引发裂缝、渗漏水等问题。施工中通过优化后浇带封闭方法,采用快易收口网将后浇带两侧封闭,混凝土无渗漏;改进支撑方法,后浇带两侧梁板受力稳定均衡,有效控制沉降,保证了后浇带的整体性,保障了后浇带的施工质量。 There are many post-pouting concrete belts in the foundation of Guomai Building project and improper construction may easily cause cracks and water leakage. During construction, post-pouring belt blocking method is optimized and high ribbed formwork is used to block both sides of post-pouring belt and successfully prevent concrete leakage; supporting method is improved to realize stable and balanced forces on both sides of beam slab, effectively control settlement and ensure the integrity and construction quality of post- pouring belt.
作者 杜志强
出处 《建筑技术》 2013年第5期460-462,共3页 Architecture Technology
关键词 后浇带 混凝土 收口网 支撑 post-pouring belt concrete high ribbed formwork support
  • 相关文献

参考文献5

二级参考文献5

  • 1.混凝土结构设计规范(GBJ10-89)[M].中国建筑工业出版社,1989..
  • 2(JGJ3—2002).高层建筑混凝土结构技术规程.[S].,2002..
  • 3.混凝土结构设计规范(GBS0010-2002)[M].中国建筑工业出版社,2002..
  • 4GB50208-2011,地下防水工程质量验收规范[S].
  • 5DB11/581--2008.轨道交通地下工程防水技术规程[S].

共引文献2872

同被引文献6

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部