四车道大断面浅埋偏压隧道CD法开挖数值模拟分析 被引量:6

The Numerical Simulation Analysis with The Excavation Method of CD in Shallow Bias Tunnel with Four Lane Large Section
下载PDF
导出
摘要 基于某偏压公路隧道的设计、施工以及地质情况,采用有限元软件midas模拟CD法不同顺序开挖隧道的施工过程,对比分析围岩位移以及支护内力情况。结果表明:从埋深小的一侧开挖比从另一侧开挖的隧道围岩位移、支护内力值都要小。最后经过综合分析,确定了从埋深大的一侧导坑开挖为优选方案,可为同类隧道的设计、施工和研究提供有益的借鉴和参考。 According to the design,the construction and the geological condition of one unsymmet- rical road tunnel ,The simulation is carried out by midas to study the displacements of surrounding rock and the Internal force of supportingstructure in CD method. The simulation results indicate that both the displacements of surrounding rock and the Internal force of supporting are smaller with excavating tunnel from the shallow side by comprehensive analysis, excavating tunnel from the shallow side is the optimal- choice. This study aims to provide reference to similar tunnel design and construction.
出处 《公路工程》 北大核心 2013年第2期137-141,共5页 Highway Engineering
关键词 偏压隧道 大断面 CD法 数值模拟 Bias tunnel Large section CD method Numerical Simulation
  • 相关文献

参考文献6

二级参考文献31

共引文献1124

同被引文献41

引证文献6

二级引证文献10

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部