楼排隧道衬砌结构安全评估 被引量:2

The Safety Assessment about Lining Structure in Pai Lou Tunnel
下载PDF
导出
摘要 排楼隧道洞口段处在Ⅴ级围岩中,围岩自稳能力差,对隧道衬砌结构带来不利的影响。本文采用荷载结构法对Ⅴ级围岩衬砌结构进行了静力计算,得出初期支护和二次衬砌的最大轴力、最大弯矩,以此来评价衬砌结构的稳定性。 Pai Lou tunnel entrance section is in the Five grade surrounding rock, and the stability of surrounding rock is poor,which has a negative impact on the tunnel lining structure. This paper carry out a static calculation on the lining structure by load structure method, obtain the initial maximum axial force and the maximum bending moment, evaluate the stability of lining structure.
作者 徐国庆
出处 《公路工程》 北大核心 2013年第2期165-169,共5页 Highway Engineering
关键词 隧道 V级围岩 衬砌 轴力和弯矩 稳定性 tunnel surrounding rock lining axial force and bending moment stability
  • 相关文献

参考文献4

  • 1路美丽,刘维宁,罗富荣,李兴高.隧道与地下工程风险评估方法研究进展[J].工程地质学报,2006,14(4):462-469. 被引量:98
  • 2李冬梅,仇文革.矿山法施工山岭隧道风险指标体系[J].岩土隧道工程技术.2007(1):547-551.
  • 3彭立敏,施成华,安永林,等.浏阳河隧道施工关键技术及风险管理研究[R].长沙:中南大学土木建筑学院,2009.
  • 4JTGD70-2004.公路隧道设计规范[S].[S].,..

二级参考文献35

  • 1金锋.风险管理在城市轨道交通建设中的应用[J].都市快轨交通,2005,18(1):1-4. 被引量:16
  • 2何孝贵,牛志平,蔡雪峰.北京地铁五号线暗挖施工技术方案选优方法探讨[J].土木工程学报,2004,37(9):83-85. 被引量:4
  • 3Eskesen S. D, Tengborg P. R, Kampmann J, Veicherts T. H..Guidelines for tunnelling risk management : International Tunneling Association, Working Group No. 2 [ J ]. Tunneling and Underground Space technology, 2004, ( 19 ) :217 - 237.
  • 4Al - Bahar J. F.. Systematic risk management approach for construction projects [ J ]. Journal of Construction Engineering and Management ,1990,116(3 ) :533 -546.
  • 5Einstein H, Chiaverio F, and K & ppel U.. Risk analysis for the Adler tunnel[J ]. Tunnels & Tunnelling, 1994, 2,6 ( 11 ) : 28- 30.
  • 6Sturk R. , Olsson L. and Johansson J.. Risk and decision analysis for large underground projects as applied to the Stockholm Ring Road Tunnels [ J]. Tunnelling and Underground Space Technology, 1996,11(2): 157-164.
  • 7Kampmann J, Eskesen S. D, Summers J. W.. Risk assessment helps select the contractor for the Copenhagen Metro System [ A ].Proceedings of the world tunnel congress 98 on tunnels and metropolises[C], 1998,(1): 123-128.
  • 8ISaksson M. T, Reilly J. J, Anderson J. M.. Risk mitigation for tunnel projects - A structured approach [ A ]. Proceedings of the world tunnel congress99 [ C ], 1999, (2) : 703 - 711.
  • 9ISaksson M. T.. Tunnelling in poor ground - choice of shield method based on reliability[A]. Proceeding of the XITH Danube-European Conference on soil mechanics and geotechnical engineering[ C ], 1998,527 - 534.
  • 10Snel A. J. M, Van Hasselt D. R. S.. Risk management in the Amsterdam North/South Metro line: A matter of process - communication instead of calculation [ A]. Proceedings of the world tunnel congress99 [ C ], 1999,179 - 186.

共引文献927

同被引文献14

引证文献2

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部