基于改进的AHP-模糊综合评价法在呼和浩特抽水蓄能电站项目施工进度控制评价中的应用 被引量:1

Application of modified AHP based fuzzy comprehensive evaluation method to evaluation of construction progress control for project of Hohhot Pumped Storage Hydropower Station
下载PDF
导出
摘要 结合呼和浩特抽水蓄能电站下水库施工项目的特点和实际情况,构建了施工单位进度控制评价模型,用改进的层次分析法并结合模糊综合评价法,对评价指标进行综合评判。通过科学合理评价,明确了施工优势与不足,对加强进度控制具有借鉴意义。 Combined with the characteristics and actual condition of the construction of the lower reservoir of Hohhot Pumped Storage Hydropower Station, a model for evaluation on the construction progresses of the construction enterprises is established herein, and then a comprehensive evaluation is made with the modified hierarchy analysis integrated with the fuzzy comprehensive evaluation method. Through a scientific and reasonable evaluation, both the advantage and shortage of the construction are defined; which has reference significance for strengthening the construction progress control.
作者 槐菁
出处 《水利水电技术》 CSCD 北大核心 2013年第5期73-76,共4页 Water Resources and Hydropower Engineering
关键词 施工进度控制 层次分析法 模糊综合评价法 呼和浩特抽水蓄能电站 construction progress control hierarchy analysis method fuzzy comprehensive evaluation method Hohhot Pumped Storage Hydropower Station
  • 相关文献

参考文献4

二级参考文献21

共引文献461

同被引文献9

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部