摘要
依托南京三江口节点护岸加固工程,以施工中先进生产工艺为基础,通过对混凝土透水框架项目进行深入细致的现场研究,采用写实法提出混凝土透水框架预制生产定额及抛投定额两项确定性建议值,形成混凝土透水框架定额中最关键的两项要素,进一步完善了混凝土透水框架定额体系。
Relying on the bank revetment project of Nanjing Sanjiangkou joint and based on the advanced production process in the construction, through detailed site investigation of the concrete water permeable frame project, the suggested values for precasting production quota and casting quota of concrete permeable frame were proposed realistically, which formed the two key factors in concrete permeable frame quota, and the quota system of concrete permeable frame was further improved.
出处
《工程建设》
2013年第2期57-62,共6页
Engineering Construction
关键词
混凝土透水框架
新型护岸
定额
concrete water permeable frame
new type of bank revetment
quota