摘要
中国葛洲坝集团公司在三峡工程混凝土施工中 ,通过近两年时间的实践与探索 ,逐步掌握了ROTEC塔带机及供料线的应用 ,并对塔带机运行中存在的问题进行总结 ,提出了相应的完善措施。
During construction of the Three Gorges project, the China Gezhouba Construction Group has mastered gradually the use of ROTEC towerbelts and their feeding lines in practice for two years, and has analyzed and taken the improvement measures to issues in operation of the equipment, which provides the hydro construction industry with more successful and scientific methods for the further application of the towerbelts.
出处
《中国三峡建设》
2000年第11期9-11,共3页
China Three Gorges Construction
关键词
塔带机
温度回升
瞬间冲击力
骨料分离
塌落度、砂浆损失
措施
towerbelt
temperature rising
instantaneous impact
aggregate segregation
slump
mortar loss
measures