盾构掘进穿越海堤稳定性分析与工程控制措施 被引量:2

Stability Analysis for Seawall with Shield Tunnel Digging and Engineering Control Measures
下载PDF
导出
摘要 结合盾构穿越工程实例,对海堤沉降变形和整体抗滑稳定系数进行计算和分析。结果表明:海堤最大沉降为9.2 mm,穿越位置海堤整体抗滑稳定系数略有降低,但满足规范要求的抗滑稳定安全系数,在正常施工条件下,不会造成海堤整体失稳。为消除沉降对堤身土体的密实度和防渗性能的不利影响,宜对受影响的区域土体进行灌浆加固。 Combined with the engineering examples of shield tunnel digging, the theoretic analysis method and numerical simulation are adopted here to calculate the ground settlement and anti-slide coefficient of seawall. The results show that the maximum ground settlement is 9.2 mm, and the seawall anti-slide stability coefficient decreases slightly, but it is in a safe range, so it is not able to couse the instability of the seawall. In order to eliminate the adverse effects of the settlement on the density and anti-seepage properties of the seawall, the appropriate control measures such as grouting should be carry out.
出处 《水利与建筑工程学报》 2013年第3期63-66,共4页 Journal of Water Resources and Architectural Engineering
基金 国家自然科学基金项目(41101519)
关键词 盾构掘进 PECK公式 数值模拟 稳定性分析 控制措施 shield tunnel digging Peck formula numerical simulation stability analysis control measure
  • 相关文献

参考文献5

二级参考文献59

共引文献630

同被引文献24

引证文献2

二级引证文献15

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部