井底车场大跨度交岔点加固支护技术实践

Practice on Reinforcement and Supporting Technology of Big Span Intersection in Shaft Bottom
下载PDF
导出
摘要 察哈素煤矿井底车场1#交岔点埋深430 m,为大跨度交岔点,其结构形式为牛鼻子交岔点。起初采用锚杆加喷射混凝土支护交岔点,交岔点变形严重。经分析研究决定采用U型钢套棚+锚网喷综合支护方法加固交岔点,并进行了矿压观测。由矿压观测结果可知,该支护方法合理,支护效果良好。 The buried depth of the 1^* intersection in shaft bottom of Chahasu Coal Mine is 430 m. It belongs to the intersection with large span,and the structure is ox-nose-like intersection. At first,the intersection was supported by anchor and shotcreting, but serious deformation happened on the intersection. Therefore,a new supporting method was proposed by using U steel racking girders + anchor, wire mesh,shotcreting. Relevant pressure observation was also carried out. The results show that,this supporting method is reasonable and has gained good supporting effects.
作者 田灵涛 刘平
机构地区 察哈素煤矿
出处 《中州煤炭》 2013年第5期85-86,共2页 Zhongzhou Coal
关键词 大跨度交岔点 综合支护 矿压观测 big span intersection comprehensive supporting rock pressure observation
  • 相关文献

参考文献3

二级参考文献3

共引文献21

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部