摘要
泵闸枢纽工程是解决城市排水问题的有效途径之一。结合上海朱泖河泵闸工程,针对因结构布置上要满足该泵闸运行条件而产生的较复杂的水流问题,采用三维有限元计算手段模拟了泵闸运行时进出水池的水流状况,与模型试验结果进行对比,数值模拟结论与模型试验结果相符,并提出改善措施解决了因导流隔墙绕流现象导致的进水池水流不均问题。
The pump brake hub engineering is one of the means of solving water drainage in urban areas. Based on the pump brake projects of the Zhumao River in Shanghai. The three-dimensional finite element is used to simulate the water flow in time of the pump brake's operation. Numerical simulation conclusions are compatible with experiment results. Some improvement measures have been put forward to solve uneven water flow.
出处
《中国农村水利水电》
北大核心
2013年第5期133-136,共4页
China Rural Water and Hydropower
基金
国家自然科学基金资助项目(51079044)
关键词
竖井贯流泵
泵闸枢纽
湍流模型
刚盖假定
shaft tubular pump
pump brake hub
turbulence model
rigid lid hypothesis