1119MW核电机组半速汽轮机主汽阀和调节阀调整试验 被引量:2

Commissioning Test of Stop Valve and Control Valve for Semi-speed Steam Turbine in 1119 MW Nuclear Power Plant
原文传递
导出
摘要 介绍了红沿河核电站1号机组汽轮机主汽阀和调节阀布置、结构特点;论述该机组主汽阀和调节阀的调整过程,包括阀位反馈整定、阀门开关时间调校、阶跃响应测试等;对一些重要技术指标进行了分析并给出了调校办法。此调整经验可供同类工程调试专业人员参考。 This paper introduces the layout and turbine in Hongyanhe Nuclear Power Plant, as well feedback, the adjustment and calibration of valve indexes were analyzed to give adjustment methods, structure characteristics of stop valves and control valves of No. 1 steam as the valves' commissioning process, including setting of valve position switching time, step response test. Finally, some important technical which could provide references for similar projects' commissioning
出处 《电力建设》 2013年第5期62-65,共4页 Electric Power Construction
关键词 核电站 汽轮机 主汽阀 调节阀 调整 nuclear power plant steam turbine stop valve control valve commissioning
  • 相关文献

参考文献10

二级参考文献7

共引文献38

同被引文献15

引证文献2

二级引证文献10

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部