期刊文献+

某核电厂现浇混凝土蜗壳模板施工技术探讨 被引量:1

Discussion on a nuclear electrical power plant in scroll case concrete formwork construction technology
下载PDF
导出
摘要 以某核电厂PX泵房工程为例,介绍了蜗壳模板的安装工艺,同时选取蜗壳代表性截面对蜗壳模板过程中抗浮、抗滑、支撑系统等进行了详细计算,通过对PX泵房蜗壳模板施工技术的探讨,为现浇混凝土蜗壳提供了一种安全可靠且经济适用的施工方法,以供其他核电项目施工参考。 This paper takes a nuclear power plant PX pumping station project as an example, introduction of the installation technology of spiral case template, at the same time, selection of representative section of the volute template in the process of anti-floating, anti-slide, supporting system are calculated in detail, provides a construction method for safe and economical discussion on the formwork construction technology of pump volute PX for cast-in-place concrete volute, for other project construction.
出处 《山西建筑》 2013年第18期87-89,共3页 Shanxi Architecture
关键词 PX泵房 蜗壳 施工技术 PX pump scroll construction technique
  • 相关文献

参考文献1

二级参考文献2

  • 1JGJ130-2001.建筑施工扣件式钢管脚手架安全技术规范[S].[S].,..
  • 2JGJ33-2001.建筑机械使用安全技术规程[S].[S].,..

共引文献3

同被引文献5

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部