摘要
介绍了球式热风炉前置预热技术在柳钢2号高炉(2650m3)的应用情况:通过配套采用前置燃烧炉和板式预热器组合预热工艺,稳定和提高热风炉风温到1200℃。
Application of advance preheating technology of pebble stove in No.2 Blast Furnace (2 650 m3) was introduced: the blast temperature can be kept and improved to 1 200 ~C by adopting the combined preheating process of the advance combustion furnace and the plate-type preheater.
出处
《柳钢科技》
2013年第3期25-27,54,共4页
关键词
高炉
风温
球式热风炉
前置预热
板式预热器
Blast Furnace
Blast Temperature
Pebble Stove
Advance Preheating
Plate -type Preheater