摘要
通过参与西安地铁2号线车辆的调试、预验收、综合联调及演练的整个过程,列举出综合联调及演练期间车辆专业人员的主要任务,如车辆预验收工作的开展、各种检修规程及应急类文本的验证、员工技术技能的提高等。并探讨了综合联调及演练期间车辆专业人员重点工作的推进及注意事项。
Base on the working process of vehicle adjust- ment, advance acceptance check, com composite adjustment and drilling on Xi'an metro Line 2, the main works of the professionals in composite adjustment and drilling are listed, such as the process acceptance check in advance, various dircctive rules in overhaul, validation of drilling text, improvement of employees' skills, etc., the main works and notable matters are put forward for further discussions.
出处
《城市轨道交通研究》
北大核心
2013年第6期26-28,共3页
Urban Mass Transit
关键词
城市轨道交通车辆
车辆预验收
综合联调
应急预案
urban rail transit vehicles
vehicles advance acceptance check
composite adjustment
contingency plan