摘要
针对如何解决承包商和非承包商双方共同作用下工程延期的计算这一难点问题 ,运用网络分析法 ,通过对承包商单独作用和非承包商单独作用以及承包商和非承包商共同作用网络状态图的分析比较 ,提出了“附加值”的概念 ,建立了相应的数学模型 ,并给出了具体的计算步骤 。
In order to solve the problem encountered in the calculation of engineering prolongation under the bilateral influences of contractors and non contractors,this paper makes a comparison between the network states under the unilateral influence of contractors or non contractors and bilateral influences of the both by using network analysis. A novel concept “additional value” is presented. A corresponding mathematical model and detailed procedure of calculation are given,which provides a practical approach for the calculation of engineering prolongation under the affection of double factors.
出处
《合肥工业大学学报(自然科学版)》
CAS
CSCD
2000年第4期572-576,共5页
Journal of Hefei University of Technology:Natural Science
关键词
双方因素
工程延期
附加值
工期延长值
数学模型
double factors
the prolongation engineering
addtional value
the extension time of project