随着计算机技术的发展,模拟程序受到各生产企业的重视,利用模拟程序可以对许多重要的生产环节进行可靠性验证。综采放顶煤环节在煤矿开采中有着重要的位置,文章利用计算机模拟技术对该环节的14个元素进行模拟,通过唐山矿一号井的实际模拟情况验证该程序的正确性,为今后的煤矿生产模拟程序开发提供了依据。
With the development of computer technology,the simulation program got high attention by the production enterprises,using the simulation program can carry out reliability verification for many important links in the production chain.The fully mechanized top coal caving process in coal mining has an important position.This paper used the computer simulation on the link of the 14 conducting elements simulation,verified the correctness of program through the actual simulation of Tangshan mineral No.1 well,provided the basis for the future coal mine production simulation program developement.
出处
《煤炭技术》
CAS
北大核心
2013年第6期68-70,共3页
Coal Technology
关键词
计算机模拟
放顶煤
综放工作面
computer simulation
top coal caving
fully mechanized caving face