基础设施的修建对南水北调中线工程串流区的影响分析

Impact of Infrastructure Constructions on Over-flow Area of the Mid-Route Project of the South-to-North Water Transfers
下载PDF
导出
摘要 现以赵庄南沟串流区为例,分析了由于在初步设计修改阶段流域内修建了高速公路,改变了南水北调总干渠以上的水文情势,对串流片内的穿河建筑物规模和安全产生的影响。在初步设计修改阶段,根据最新的情况和研究结果,修改了交叉建筑物的规模和防洪水位等,保证了建筑物本身和总干渠的安全。 In this study, the over-flow area of Zhaozhuang Nan River is selected as an example. In the preliminary design phase, it has changed the hydrological regime above the main channel due to construction of the highway in the basin. Besides that, it also affects the scale and security of crossing-river buildings. In the preliminary design modification stage, it re-modifies the size and flood control water level of the building based on the latest situation in order to ensure the safety of the buildings and the main channel.
出处 《南水北调与水利科技》 CAS CSCD 北大核心 2013年第B01期115-117,共3页 South-to-North Water Transfers and Water Science & Technology
关键词 南水北调中线工程 串流区 基础设施修建 影响分析 二维非恒定流数学模型 总干渠 调洪演算 Mid-Route Project of the South-to-North Water Transfers over-flow area infrastructure construction impact analysis 2-D unsteady flow mathematical model main channel flood routing.
  • 相关文献

参考文献2

共引文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部