摘要
为解决在各种复杂环境条件下地铁车站的建设,该文通过对北京地铁14号线11标段车站建设工法的研究,进行了大直径盾构扩挖修建车站的探索。
In order to solve the construction of metro station under various complex environmental conditions,the article studies the construction methods of stations in Contract 11 of Beijing Metro Line 14,and discusses the excavation construction of station by large-diameter shield.
出处
《城市道桥与防洪》
2013年第5期184-185,193,共3页
Urban Roads Bridges & Flood Control
关键词
大直径盾构
扩挖
车站
北京市
large-diameter shield,excavation,station,Beijing