摘要
结合箱式变电站下沉式安装的特点,对其安装的流程及要点作了详细归纳,就吊装作业、电气调试、设备运行等安全保障方面需采取的措施作了介绍,以积累相关安装经验。
Combining with sunken installation features of box-type substation, the paper summarizes its installation procedures and points, and introduces security guarantee measures in perspectives of hoisting, electric adjusting and equipment operation, with a view to accumulate relevant installation experience.
出处
《山西建筑》
2013年第19期74-76,共3页
Shanxi Architecture
关键词
箱式变电站
安装
安全
检查
box-type substation
installation
security
check