摘要 根据新建机组现场实际情况 ,通过优化燃烧调整内容 ,强化冷态工作过程 ,摸索调试阶段旨在保证机组稳定、安全完成整套试运的燃烧调整简化方式。 According to the actual site conditions of a newly constrcted generating set,by optimizing the regulation contents and strengthening the cool-state working process,the simplified combustion regulation mode were groped out to aim at ensuring the completion of complete set commissioning test of generating set stably and with safety.
出处 《东北电力技术》 2000年第8期6-10,共5页 Northeast Electric Power Technology
关键词 燃烧调整 运行方式 参数控制 锅炉 600MW机组 Combustion regulation Complete-set commissioning test Operation mode Parameter control
  • 相关文献

同被引文献3

  • 1张朝阳,李卫华,宋兆星.600MW超临界直流炉机组协调控制系统策略[J].华北电力技术,2007(1):24-28. 被引量:29
  • 2黄新远.电站锅炉运行与燃烧调整[M].北京:中国电力出版社.2003.
  • 3Tawney R, Khan Z, Zachary J. Economic and performance evaluation of heat sink options in combined cycle applications [A]. Proceeding of Turbo Expo [C]. ASME/IGTI Turbo Expo. Atlantic, Georgia, USA, 2003.

引证文献1

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部