桥电六期3#锅炉调试总结

3~# Boiler debugging summarization in the sixth Phase of QiaoTou Thermal Power Plant
下载PDF
导出
摘要 对于火力发电机组 ,机组启动调试是电力建设施工的最后一道工序 ,其质量的优、劣是直接关系到机组的安全、顺利投产以及充分发挥生产效益的一个关键。而桥电六期 3#锅炉调试是我专业目前所从事的最大一台机组的调试 ,因此 ,认真总结调试经验就显得非常重要。文章讲述了我专业对桥电 3#锅炉启动调试前的检查、试验和准备工作以及调试项目、程序和最后的结论。 WT5”,6BZ]To thermal power set,starting set debugging is a last working procedure to building of electric power.Whether it's quality good or not a crux and it will effect set's safety,successfully goes into operation,and fully brings into play productive benefit,3\+# boiler debugging in the sixth Phase of QiaoTou is a biggest set debugging that our specialty engaged in,so it is very important to summarize debugging work hardly.The paper tells reader that our specialty did the work is checked,experimented,prepared and debugged the item and program before debugging to 3\+# boiler in the sixth Phase of QiaoTou.
作者 刘荣礼
出处 《青海电力》 2000年第3期44-47,共4页 Qinghai Electric Power
关键词 锅炉 调试 制粉系统 燃烧调整 Boiler,Debugging
  • 相关文献

参考文献3

  • 11,桥电六期3#锅炉调试记录
  • 22,杨佐林.锅炉附属设备启动调试.西北电力建设调试施工研究所
  • 33,刘衍.N125机组锅炉运行规程.桥头发电厂 2000-03-21

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部